Operation of graphite heat exchanger

Apr 08, 2022

Matters Needing Attention in the Use of Graphite Heat Exchangers

 

Pay attention to the effect of external force on graphite equipment. The physical characteristics of graphite itself determine its poor shear performance, especially between layers is very easy to be damaged by external forces, so in the process of installation and daily maintenance of graphite heat exchanger, special attention should be paid to the damage caused by external forces.

 

When lifting graphite equipment, we must lift it smoothly, keep the force of the equipment uniform, lift and choose no wind or breeze for lifting, do not accelerate, as far as possible to reduce the effect of external force on the graphite heat exchanger. After the graphite heat exchanger is installed, it is necessary to pipe and tighten it.

 

In the process of piping, assembly errors should be reduced as much as possible, and compensators should be installed at the contact end of the graphite heat exchanger, so as to reduce the stress caused by vibration and thermal expansion and contraction. When fastening the flange of graphite heat exchanger, it must be tightened diagonally with a torque wrench in strict accordance with the torque size required by technical documents to prevent excessive or uneven force.

 

The coolant used for graphite heat exchanger should be as hard as possible. Graphite heat exchanger has high requirement for cooling medium because of its special structure. In the process of the cooling medium ejection through the nozzle, the graphite heat exchanger through evaporation to take away a lot of heat and play a cooling role. Evaporation will inevitably lead to supersaturation of the cooling medium.

 

If the hardness of the cooling medium is higher, it will inevitably lead to a large amount of salt precipitation. Because the nozzle of the graphite heat exchanger is only 2mm in size, the salt constantly precipitated will plug the nozzle, reduce and gradually affect the working efficiency of the graphite heat exchanger, and eventually the graphite heat exchanger will stop working because the outlet temperature is too high, and damage the graphite heat exchanger.

 

In industrial chemical production, we usually choose water as the cooling medium, so the hardness of the coolant used must be very low, especially the concentration of calcium and magnesium ions should be as small as possible. Through a lot of practice, we finally choose demineralized water as the cooling medium of the heat exchanger, and keep the cooling medium weak acidic, so as to prolong the cleaning cycle of the graphite heat exchanger as much as possible.

 

Use as little demineralized water as possible. Due to the high production cost of demineralized water, we must try to reduce its use as much as possible in daily use. During the action of the cooling medium, its own temperature will gradually increase, and the heat treatment efficiency will gradually decrease. To compensate for the effect of increased temperature on the reduced heat treatment efficiency, we always keep the coolant in a state of overflow.

 

Through the interlocking effect of liquid level and water replenishment, the above-mentioned adverse effects can be eliminated by replenishing the cooling liquid at the bottom temperature. Since the whole system includes a cooling device and a gas scrubbing device, and the gas scrubbing device does not require high water quality, we set up a separate cooling liquid circulating water tank, which is specially responsible for replenishing the demineralized cooling liquid, which can make the economic investment better.

 

Steps for cleaning graphite heat exchangers and choice of cleaning fluid. After using the graphite heat exchanger for a long time, the nozzle of the graphite heat exchanger will be partially blocked. Therefore, it should be cleaned according to the timing of production shutdown and maintenance. The specific cleaning method must be determined in combination with the material properties of the supporting pipelines and equipment. The material of the water storage tank of this system is FRP, the pump is PVDF lined, and the pipes and valves are all made of PP.

 

Therefore, we choose 5% concentration of hydrochloric acid as the cleaning liquid. First, we add 5% hydrochloric acid liquid to the circulating water tank to ensure that the liquid level of the hydrochloric acid liquid is higher than the inlet of the pump, and at the same time release the low liquid level interlocking device. Next, empty the buffer tank and turn on the circulating pump for about 5 minutes.

 

In the process of hydrochloric acid cleaning, the reading of the flowmeter must be carefully observed. When the reading of the flowmeter is consistent with the design flow, the pump can be stopped. Then, the hydrochloric acid liquid was drained, and low-hardness water was added for repeated cleaning until the pH value returned to about 6. Finally, restore the original chain signal, add demineralized water, and reuse the equipment.

 

Emergency measures should be considered for emergencies. When the entire plant is shut down due to an emergency, there must be emergency measures to be used in conjunction with the graphite heat exchanger. Since the inlet temperature of the graphite heat exchanger is 600°C, the outlet temperature must be lower than 70°C. In a sudden state, the front thermal oxidizer will stop immediately, but its residual heat will be released. In order to ensure the safe use of the whole set of equipment, we should be equipped with an emergency water tank, and store enough demineralized water to eliminate residual heat, and cooperate with the self-provided generator to eliminate hidden dangers.

 

The impact of the first entry of the coolant into the graphite equipment must be reduced. The impact resistance of graphite material is poor, so it must work together in parallel with the buffer tank to reduce the impact force on the equipment when the cooling medium enters the graphite heat exchanger for the first time.

 

Coolant circulation pump should be used and standby. Circulating cooling temperature is relatively high, generally maintained at about 60℃. The stability of the pump is also very high, the circulation pump must be stable to provide the design flow, to ensure the normal work of the heat exchanger. Finally, for later maintenance and quick emergency response, we usually set up a use and a standby pump to reduce unnecessary shutdown and production losses.

 

https://www.shj-carbon.com/graphite-products/graphite-machined-products/graphite-tube-for-heat-exchanger.html